100 Mega Watt Temporary Power Station
Industry
Power | 2017-18
Client
Aggreko
Scope of Work
Installation of 105 Generators and 19 Transformer C Containers to establish 105 Mega Watt Temporary Power Station.
Works included all electrical High Voltage, Low Voltage and extra Low Voltage cabling and terminations, installation of earth grids for the whole site, connections to existing power grid and all civil works required for earth grids.
Outcome
Works were required to be completed in 32 days over 2017/2018 Christmas period. Works were completed 4 days ahead of schedule.